| |
Sign
Up for E-mail Updates |
|
| |
|
|
 |
| Intersection
of Route 22 and 21 |
 |
October 7, 2010 |
 |
September 23, 2010 |
 |
September 16, 2010 |
 |
September 2, 2010 |
 |
August 5, 2010 |
 |
July 29, 2010 |
 |
July 1, 2010 |
 |
June 10, 2010 |
 |
June 3, 2010 |
 |
May 6, 2010 |
 |
April 29, 2010 |
 |
April 15, 2010 |
 |
March 11, 2010 |
|
| Riverwoods Road and
Everett Road Intersection Improvement Project |
 |
November 11, 2010 |
 |
November 4, 2010 |
 |
October 21, 2010 |
 |
October 14, 2010 |
 |
September 23, 2010 |
 |
September 2, 2010 |
 |
August 19, 2010 |
 |
August 5, 2010 |
 |
July 29, 2010 |
 |
July 1, 2010 |
 |
June 8, 2010 |
|
|
 |
 |
Intersection of Route 22 and 21 Construction Updates
May 6, 2010
The contractor is still on schedule to start the transition into
Phase IA of the construction project. Provided
the weather and schedule cooperate, next Tuesday or Wednesday,
the contractor will be shifting the
north/south traffic of Route 21 (Milwaukee Avenue) on to the new
pavement Once that occurs, this traffic
pattern will remain for approximately two additional weeks, before
the east/west traffic of Route 22 is moved
to the new pavement. As explained in the previous update, the traffic
pattern switches have to be staged this
way to allow the contractor to modify areas deeper into the intersection,
which will allow for traffic
transitions to take place between the old and new pavement. Once
the traffic has all been moved to the newly
paved areas, that traffic pattern will remain in-place for approximately
two months. Following the completion
of those lanes, the contractor will tie everything in with the
center median work. The east/west bike path
paving was delayed, and is rescheduled to be done next week. As
a reminder, when the path is completed,
it will not be open. The contractor will remove the barricades
closing the path when it is safe for travel.
The project remains on schedule for a completion date of September
24, 2010.
Please pay close attention to the traffic control
measures, as the traffic pattern changes will take time to
become accustomed to. As always, the Village will pass along
information as it is provided to us.
As a reminder, reduced speed limits will still be in effect
in this and all construction zones, whether or not
workers are present. Drivers should continue to watch for
changing traffic patterns and use caution,
especially when workers are present. Police agencies have
zero tolerance for drivers speeding in work
zones. The minimum penalty for speeding in a work zone is
$375. Posted signs advise motorists of a
$10,000 fine and 14-year jail sentence for hitting a roadway
worker.
If you have any questions regarding this
matter, please contact Rob Horne by email at
or by phone at 847.913.2366.
|