| Intersection
of Route 22 and 21 |
 |
October 7, 2010 |
 |
September 23, 2010 |
 |
September 16, 2010 |
 |
September 2, 2010 |
 |
August 5, 2010 |
 |
July 29, 2010 |
 |
July 1, 2010 |
 |
June 10, 2010 |
 |
June 3, 2010 |
 |
May 6, 2010 |
 |
April 29, 2010 |
 |
April 15, 2010 |
 |
March 11, 2010 |
|
| Riverwoods Road and
Everett Road Intersection Improvement Project |
 |
November 11, 2010 |
 |
November 4, 2010 |
 |
October 21, 2010 |
 |
October 14, 2010 |
 |
September 23, 2010 |
 |
September 2, 2010 |
 |
August 19, 2010 |
 |
August 5, 2010 |
 |
July 29, 2010 |
 |
July 1, 2010 |
 |
June 8, 2010 |
|
|
 |
 |
Intersection of Route 22 and 21 Construction Updates
September 23, 2010
TRAFFIC PATTERN CHANGE
Currently scheduled for Wednesday, September 29, 2010
The contractor has completed the pavement work required as part
of the Stage 2 construction.
Additionally, they are very close to completing the construction
required as part of Stage 2A. The
contractor is now mobilizing to begin Stage 3 construction, which
includes tying the pavement sections
together in the middle of the paved areas, construction of medians,
and restoration work. Please pay close
attention to these changes, as it can take some time to become
accustomed to.
As part of this traffic switch, several area businesses
will be affected. Below is a list of the affected
businesses and how their access will be affected.
The commercial driveway access will be as follows:
McDonald's
- Southbound Milwaukee Avenue traffic will have full access.
- Northbound Milwaukee Avenue traffic will be able
access the Milwaukee Avenue drive,
following completion of the pavement between the north and southbound
lanes.
- Eastbound Route 22 traffic will not be able
to access the Route 22 driveway due to
construction of the permanent barrier median.
- Westbound Route 22 traffic will be able to
access the Route 22 driveway once the
westbound lanes are opened to traffic next week.
BP Amoco Gas Station
- Southbound Milwaukee Avenue traffic will have full access.
- Northbound Milwaukee Avenue traffic will not be able to access
the Milwaukee Avenue
driveway due to construction of the permanent barrier median.
- Eastbound Route 22 traffic will not be able to access the
Route 22 driveway due to construction of the permanent barrier
median.
- Westbound Route 22 traffic will be able to
access the Route 22 driveway once the
westbound lanes are opened to traffic next week.
Greenview Homes
- Southbound Milwaukee Avenue traffic will have full access.
- Northbound Milwaukee Avenue traffic will be
able to access the Milwaukee Avenue drive,
following completion of the pavement between the north and
southbound lanes.
Marathon Gas Station
- Northbound Milwaukee Avenue traffic will have full access.
- Southbound Milwaukee Avenue traffic will be able to access
the Milwaukee Avenue drives,
following completion of the pavement between the north
and southbound lanes.
As a reminder, reduced speed limits will still be in effect in
this and all construction zones, whether or not workers are present.
Drivers should continue to watch for changing traffic patterns
and use caution, especially when workers are present. Police agencies
have zero tolerance for drivers speeding in work zones. The minimum
penalty for speeding in a work zone is $375. Posted signs advise
motorists of a $10,000 fine and 14-year jail sentence for hitting
a roadway worker.
While the Village has not received any official information regarding
a completion date revision, based on
the remaining work to be completed, our expectation is mid to late
October at this point. We will notify
you of any changes as soon as they are provided to us.
If you have any questions regarding this matter, please contact
Rob Horne by email at
or by phone at 847.913.2366. As always, the Village will pass along information
as it is provided to us. |