Tollway Bridge on Route 22 Construction Updates
August 6, 2009
Revised Traffic Patterns and Bridge Demolition Occurring on Route
22 at Tollway
The contractor continues the construction activity on the north
side of Route 22, with a specific concentration at
the Bridge. The contractor has scheduled a temporary lane closure
on the Tollway during the overnight hours
on August 19th and 20th to erect structural beams. Additionally,
during the week of August 17th, there will be a
traffic reconfiguration that will affect Hewitt Drive at Route
22. Please pay attention to the posted signage, as
changes to the traffic patterns will take time to become accustom
to, especially during the reconfiguration of the signals.
The Route 22 traffic configuration is expected to
remain in-place until the projected completion date. The
contractor remains on schedule to complete the project in November
2009.
The Village will pass along pertinent information as it becomes
available to us.
Caution, reduced speed limits are in effect 24/7
in this and all construction zones, whether or not workers are
present. Drivers should continue to watch for changing traffic
patterns and use caution, especially when workers
are present. Police agencies have zero tolerance for drivers
speeding in work zones. The minimum penalty for
speeding in a work zone is $375. Posted signs advise motorists
of a $10,000 fine and 14-year jail sentence for
hitting a roadway worker.
If you have any questions regarding this matter, please contact
Rob Horne by email at
or by phone at 847.913.2366.
|